Paverate

Base Course

material

Bottom structural asphalt layer (thickest). Provides the primary load-bearing capacity for the pavement structure.

Compaction

process

Roller passes to reach target density; measured by stick check. Typically requires 95-100% of max dry density per GDOT specs.

GDOT Table 12

reference

Spread rate tolerance table. Base: ±55 lbs/SY, Intermediate/Wearing: ±27.5 lbs/SY, OGFC: ±7 lbs/SY, PEM: ±10 lbs/SY from designated rate.

GDOT Table 4

reference

Minimum air temperature table for asphalt placement. Specifies required temperatures based on lift thickness (e.g., 1 inch or less requires 55°F minimum).

Intermediate Course

material

Middle layer between base and wearing course. Provides additional structural support and smoothness.

lbs/SY

unit

Pounds per Square Yard. Standard unit for spread rate (how much asphalt per area). Controls thickness and density of the asphalt mat.

Lift

measurement

Single layer of asphalt placed in one pass. Multiple lifts may be used to achieve total pavement thickness.

MTV

equipment

Material Transfer Vehicle. 24-ton machine that sits between the dump truck and paver, providing continuous material flow and remix action.

OGFC

material

Open-Graded Friction Course. Porous asphalt surface mix that allows water to drain through, improving wet-weather traction.

PEM

material

Polymer-Enhanced Membrane (also called Polymer-Enhanced Mixture). Asphalt surface treatment that provides enhanced durability and resistance to cracking.

Screed

equipment

Heated plate on back of paver that levels and smooths the asphalt. Controls the final mat thickness and surface texture.

Spread Rate

measurement

How much asphalt per square yard (lbs/SY). Controls thickness and density. Calculated as thickness (inches) × 110 lbs/SY per inch.

Station

unit

100 linear feet of road. Standard civil engineering unit for measuring roadway distances.

Stick Check

process

Manual thickness measurement of asphalt mat behind the screed. Measures loose material height to verify proper compacted thickness (loose height = compacted × 1.25).

SY

unit

Square Yard. Equal to 9 square feet. Standard unit for paving quantities and area calculations.

Tack Coat

material

Asphalt emulsion sprayed on existing pavement to bond new layer. Application rate varies by surface condition (typically 0.04-0.12 gal/SY).

Tack Rate

measurement

Volume of emulsion applied per square yard before paving. Must be within GDOT Table 2 range for the surface type being bonded.

Truck Load

measurement

Nominal tons per dump truck, typically 18-20 tons. Actual capacity varies by truck and local regulations.

Wearing Course

material

Top surface layer that traffic contacts directly. Must meet friction, smoothness, and durability requirements.

Offline